REDELIVERY UNDER TIME CHARTERS
NOTES FOR A SEMINAR
GIVEN TO THOMAS MILLER
ON FRIDAY, 14TH JULY 2006
BY DAVID HUGHES
In this paper, I propose to review the authorities relating
to redelivery under time charters and then see what principles
can be derived from them. In the process, we shall hopefully
cover the types of problems, or some of them, which you or your
members may be likely to come across.
The Charter Period
Consider the various descriptions to be derived from the cases.
1. Watson Steamship –v- Merryweather
1913 Atkin J
The vessel HUGIN was chartered for a
period
“from May 15/31 1912, until 15/31 October 1912”,
and
“hire to continue until her redelivery to owners (and
then in handwriting) between 15th and 31st October ,1912”
Vessel was redelivered after the 31st
October and the resultant claim was for the market rate from
that date until the actual redelivery. The claim succeeded but
the reasoning of the Judge was that the addition of the handwritten
words had the effect of negativing the extension of the contract
beyond the 31st October. Otherwise a margin would have been
implied. It made time of the essence and accordingly Owner’s
claim succeeded.
2. The London Explorer- HL 1967
The charter period was
“from the time of delivery, for
12 months 15 days more or less in Charterers option”
She was delivered on 29 December 1967
but her final voyage was from Japan with cargo for New Orleans
and Houston. She was unfortunately caught up in strikes at both
discharge ports and could not be redelivered until 24th April
1969, well beyond the original date for redelivery. The question
was at what rate should hire be paid for the period beyond the
contractual redelivery date- assumed to be 13 January on the
basis of the 15 days margin in the above wording. But in this
case it was the Charterers argued that the additional amount
should be damages assessed at the market rate because the market
had fallen for that period. So Owners were saying that the Charter
should continue beyond that at the charter rate. In the event
the Owners arguments succeeded and the extra hire had to be
paid at the charter rate.
3. The Dione 1975 –CA (Denning, Orr & Browne)
This was on a Baltime 1939 Form and the
charter was for
“a period of 6 months time charter
20 days more or less in charterers’ option from the time
the vessel is delivered and placed at the disposal of the Charterers…”
She was delivered on 8th March 1970 and
sent on 2 voyages. On 2nd August she was sent on a third voyage.Having
regard to the periods of the first 2 voyages, the charterers
could not reasonably have anticipated redelivery by 28th September
i.e. 6 months and 20 days from 8th March. A reasonable estimate
for redelivery would have been the middle of October. In fact
it was redelivered on 7th October. The charterers paid the contractual
rate of hire from the time of delivery on 8th March to that
of redelivery on 7th October. The owners claimed damages of
£6,015 (in respect of the period from 28th September)
and the matter went to arbitration and thereafter on appeal
on what was in those days a special case, the question being
whether or the construction of the charter the charterers were
or were not in breach in failing to redeliver the “DIONE”
for 8.416 days after the latest date for redelivery specified
in clause 1 of the charter; namely 20th September 1970. At first
instance before Mocatta J, it was held that the charterers were
not in breach and that owners were only entitled to no more
than nominal damages. The answer to the special case was accordingly
no. This was appealed and Denning gave a leading judgment in
which the notion of the illegitimate last voyage was introduced.
Various principles are to be derived.
(i) Where the charterparty expressly
defines the margin as 20 days more or less, it was the duty
of the charterers to redeliver the vessel by the 20 days more
i.e. by 28th September 1970.
(ii) It was illegitimate for the charterers
to send the vessel on the third voyage as they could not reasonably
have expected to complete the voyage by 28th September.
(iii) (Interestingly) by the 2 Judges
other than Denning, Orr & Browne LJJ that since the arbitrators
had held that 8.416 days were “within the reasonable elasticity
which is proper to allow” the Court could not go behind
this finding – interesting because they would have treated
that as a fact and in those days it had to be a question of
law for consideration by the Court.
(iv) Since the charterers had failed
to redeliver the vessel within the permitted margin they must
pay the charter rate up to 28th September and the market rate
thereafter.
4. The Democritos CA 1976
The duration of the NYPE Form was described
as being
“duration about 4 to 6 months”.
It was held by the Court of Appeal that
a margin should be allowed beyond the 6 months. The margin being
allowed by the arbitrators was 5 days. But in another case ¬The
“Bocimar” v. Ferenco Navigation [2002] where the
charter was for a period of 11 to 14 months and the charterers
redelivered 5 days before the expiry of the 11 months, the arbitrators
declined to imply any margin noting that the charterers could
have found further employment to bring redelivery within the
broad 3 month span. Note that a margin will not be implied where
the parties have in their charterparty expressed the charter
period as being between a certain minimum and maximum time.
This is sometimes expressed as trying to imply elasticity on
elasticity and the Courts are reluctant to do that. Similarly
where there is an additional period added by the parties themselves
such as the phrase “20 days more or less”.
5. The Sanko Honour – 15th October
1984 Hobhouse J.
“The vessel shall be delivered
by Owners as a new building unused at or off Builders’
shipyard Japan at Owner’s option and redelivered to Owners
at a port or point at sea worldwide within Institute Warranty
limits but not further in distance than Persian Gulf is from
Japan at charterers’ option.”
The vessel was redelivered at Honolulu
and the owners contended that Honolulu was not a legitimate
place to redeliver the vessel because it was further from the
Persian Gulf than Japan was. The matter went to arbitration
and the arbitrator held that it should be construed in favour
of owners. The approach of the arbitrator was criticized as
being unacceptable because he wanted simply to approach it as
the most sensible and business-like construction of the redelivery
obligation but the judge, Hobhouse J, held that the phrase “not
further in distance than the Persian Gulf is from Japan”
indicated that Japan was to be treated as the centre-point from
which the obligations of redelivery were to be regarded. The
wording of the charterparty was clear and it incorporated the
bargain which the parties made and the tribunal’s duty
was to give effect to that bargain in accordance with the words
the parties had chosen. The arbitrator’s approach was
therefore wrong and the proper construction of the charterparty
wording was the distance from Japan, and Honolulu was within
the redelivery range laid down by the charterparty and the Award
would be set aside.
6. The Artic Skou – 5th July 1985
– NYPE Form
It was concerned with what time was to
be applied in computing the period of a charterparty and specifically
whether there was a implied use of local time. The vessel was
delivered in Brazil and redelivered in Bilbao and the argument
was about 5 hours, being the time difference between the 2 regions
of delivery and redelivery. It was held that it was the actual
period elapsed which is to be used as the relevant period which
necessarily entails using the same time zone for delivery and
redelivery, as adjusted.
7. The Black Falcon – 1990 NYPE
Form (Steyn J.)
The initial period was for
“9 months, charterers’ option 3 months, charterers’
option further 3 months 15 days more or less on final period”.
There was a further addendum by which
the parties agreed that the charter was to be extended
“In direct continuation for a period of 6 or 8 months
15 days more or less in charterers’ option exact period
to be declared latest 21.12.1987.”
The charter was to continue either until
31st March 1988 or 31st May 1988.
On 22nd December 1987 the charterers
indicated that they wished to exercise the option to continue
the charter for a period of 8 months i.e until 31st May 1988.
This was rejected by owners as being a late exercise of the
option and owners treated it as a continuation for 6 months
only, and the case was concerned with the differential between
the market and charter rate and for what period. On 29th January
1988 the charterers sent the owners details of the vessel’s
intended schedule showing that the vessel would leave Europe
in March 1988 in order to perform a round voyage to India. The
owners protested but the voyage was performed and the vessel
was redelivered to the Owners on 23rd May 1988 in Europe. The
owners claimed the difference between the market and the charterparty
rate for the period 9th March to 23rd May. They declared that
the last voyage was illegitimate. And this was found to be the
case by the arbitrators: the last voyage was illegitimate and
it would not have been completed by 14th April i.e. 31st March
plus 15 days. They upheld owners’ claim for damages. The
charterers were liable accordingly to pay the market rate from
16th March to 23rd May. Held (by Steyn J.) that the period was
a true and the primary period of 6 months.
In circumstances where the owners undertook
the illegitimate last voyage without waiving their rights to
claim damages, the charterers’ obligation was to pay the
charter rate until the last admissible date for redelivery and
thereafter pay the market rate until actual redelivery. Nevertheless
the Judge varied the Award and awarded the owners the market
rate from 14th April until 23rd May. The reasoning being that
the relevant interest was the owners’ ‘expectation
interest’ which was to receive no more than the charter
rate until 14th April if the charterers had availed themselves
of the optional tolerance. He did not like the idea of owners
getting a windfall.
8. The Peonia 1990 CA
The charter period on an NYPE Form dated
3rd April 1987 for a period of
“about minimum 10 months maximum
12 months time charter. Exact duration in charterers’
option…. Charterers have further option to complete last
voyage within… trading limits”.
Delivery was on 11th June 1987. On 6th
May 1988 the charterers concluded a voyage sub-charter to carry
soya beans from the River Plate to Singapore and Butterworth,
if this had been performed, the vessel would have been redelivered
to owners no earlier than 19th July 1988. The time charter 12th
month period expired on 11th June 1988. On 11th May the owners
protested alleging that the proposed voyage was illegitimate
and asked for voyage orders which would enable the vessel to
be redelivered within 45 days i.e. by 25th June thereby giving
effect to the expression “about” in the charter.
On 17th May the owners called for voyage orders which would
enable the vessel to be redelivered within the charter period
or alternatively for payment of hire at an enhanced rate for
the duration of the voyage outside the charter period. The charterers
refused. It went to arbitration and the arbitrators held that
the provision that the charterers were entitled to order the
vessel to undertake a last voyage that started before the latest
time for redelivery i.e. 11th June as extended by any tolerance
to be implied by the use of the word “about”. The
owners appealed. At first instance Saville J, held that charterers
were not entitled to order the vessel to perform a voyage which
could not reasonably be anticipated to be completed before about
11th June 1988 and the owners were entitled to refuse to comply
with any such order – the appeal was allowed. The charterers
appealed. The Court of Appeal held
(i) where a time charter stipulated a
definite date for termination of the charter period without
any express margin of tolerance the Court’s implied a
reasonable margin of tolerance; where the parties had expressly
agreed a margin of tolerance as by agreeing a minimum and maximum
period no such margin of tolerance would be implied.
(ii) where the charterers gave orders
for the employment of the vessel which could not reasonably
be expected to be performed by the final terminal date, this
was an illegitimate last voyage and the charterers were seeking
to avail themselves of the services of the vessel at a time
when the owner had never agreed to render such services. It
was thus an order that the charterer was not entitled to give
and in doing so, the charterer committed a breach of charterparty.
If the owner complied with it, he would be entitled to payment
of hire at the charterparty rate until redelivery of the vessel
and, provided he did not waive the charterers’ breach,
to damages being the difference between the charter and the
market rate, for the period between the final terminal date
and the redelivery. In this case, the additional option to complete
the last voyage within “….trading limits”
was a right by charterers to require the owners to complete
a legitimate last voyage free of any liabilities and damages
in respect of the period between the final terminal date and
redelivery unless the unexpected delay was caused by charterers’
breach of contract – the reasoning here was that having
agreed a degree of flexibility, it was not open to either party
to have agreed impliedly or assume any further flexibility.
The case is very much concerned with the additional option to
the charterers to “complete last voyage within trading
limits” and the simplest expression of this was at first
instance by Saville J, as he then was, in which he found that
the further option gave the charterers the right to complete
a last legitimate voyage without being in breach but no right
to send the vessel on an illegitimate last voyage. It was held
in that case, strongly approved by the Court of Appeal, that
this did not extend to giving the charterers the right to order
the vessel to undertake a last voyage that started before the
last time for redelivery, as extended by the use of the word
“about”. That the was the approach of Mr Hamsher
and Clifford Clark, the arbitrators and that was held to be
wrong. On closer analysis in the Court of Appeal they go into
some detail as to what is an illegitimate last voyage. If you
did give such an illegitimate order that was a breach and an
Owner would be entitled to damages for the period between the
putative redelivery and the actual redelivery.
9. The World Symphony/World Renown 1992
CA
This was a case concerned with Shelltime
3 Form which provided
“Owners agree to let and charterers
agree to hire the vessel for a period of 6 months 15 days more
or less in charterers’ option commencing from the time
and date of delivery of the vessel for the purpose of carrying
crude oil”.
Additionally in clause 18 there was a
provision that
“Not withstanding the provisions
of clause 3…. should the vessel be upon a voyage at the
expiry of the period of this charter the charterers shall have
the use of the vessel at the same rate and conditions for such
extended time as may be necessary to the completion of the round
voyage on which he is engaged and her return to a port of redelivery
a provided by this charter…”.
The charterers exercised their option
for a 15 day extension and accordingly the latest date for redelivery
was 2250 hours on 24th December 1988. On 4th October 1988 the
“WORLD RENOWN” was en route to a laden voyage from
Sirri to Rotterdam. On that day the charterers instructed the
master that after completing discharge at Rotterdam he was to
return to Sirri and load a further cargo for carriage to Rotterdam
and Milford Haven. In the event the vessel was redelivered on
18th January 1989. The owners contended that this order amounted
to a breach of charter because it could not be complied with
consistently with redelivery of the vessel by 24th December
1988. It was held both by Hobhouse J and the Court of Appeal
that the provisions of clause 18 prevailed over those of clause
3, specifically that the charterers were entitled to the use
of the vessel at the same rate and condition as was necessary
for completion of the round voyage on which she was engaged.
Hobhouse J., at first instance, stated that the contemplation
was that the vessel would be employed on a series of round voyages
carrying cargoes of Iranian crude to consumer countries and
returning to an Iranian loading port and the round voyage referred
to in clause 18 must have been contemplated to be such a combination
of a ballast and a laden voyage. In the Court of Appeal they
held that the critical phrase was “Notwithstanding the
provisions of clause 3 hereof” which pointed at the prevalence
of clause 18 over clause 3.
10. The Gregos 1994 HL
This was a charter on the New York Produce
Exchange Form for a period of about 50 to a maximum 70 days
time charter in charterers’ option with redelivery to
be at or off a port in the Gibraltar / Hamburg range. The vessel
was delivered on 8th January and redelivery became due at the
expiry of the 70 day period on 18th March with no further tolerance
or margin. After proceeding to South America and ballasting,
the vessel performed 2 voyages from Trombetas in Brazil carrying
bauxite cargoes on the River Orinoco in Venezuela. On 9th February
before the second voyage was completed, the charterers instructed
the master to proceed from Matanzas to Palua, another port on
the Orinoco and nearer the river mouth, to load a cargo of iron
ore for delivery to Fos in France (the report wrongly states
Italy). The vessel would then have been redelivered off Gibraltar
on or before 18th March. By 25th February when the vessel completed
discharge at Matanzas, the time-table had become unworkable.
This was because another vessel had grounded in the river on
12th February and was obstructing the navigable channel between
Palua and the river mouth . In the event the vessel proceeded
to Palua and gave notice of readiness to load there at 1335
on 25th February. The owners were unwilling to proceed with
the laden voyage to Fos. The charterers insisted that the orders
were legitimate but the owners contended they were illegitimate
and they would treat the charterers as being in repudiatory
breach of the charter and withdraw the vessel. A without prejudice
agreement was entered into and the vessel performed her voyage
and she was redelivered on 26th March, 8 days late partly due
to the time spent in negotiations between 25th and 29th February.
The matter went to arbitration. The arbitrator found in favour
of owners and the charterers appealed; the issues for decision
being what date the legitimacy or otherwise of the voyage had
to be established; was that the date when the order was given,
as the charterers contended, or the date when it became effectual.
The vessel was required to comply with it as the owners contended.
Secondly, was there in this case a repudiatory breach of contract
by the charterers which entitled the owners not only to refuse
to comply with the order but also to bring the time charter
to an end by accepting repudiation. It was held at first instance
that the charterers did commit a breach of contract by failing
to deliver at the end of the charterparty period and were liable
in damages if the market exceeded the charter rate as well as
for hire until redelivery took place. The charterers had 2 separate
obligations. First, to give orders for a legitimate last voyage
and secondly to redeliver the vessel at the end of the agreed
charter period regardless of whether the orders for the last
voyage were lawful or not. The charterers’ contention
that the legitimacy of the last voyage should be established
at the date when the order was given would be rejected. It would
mean, if correct, that charterers could choose a time well in
advance of the last voyage and the instruction, if reasonable
at that time, would be binding on the vessel, regardless of
subsequent events. The charterers’ obligation was to give
a lawful order before the last voyage began; provided accepted
in advance of the last voyage, that order would remain binding.
On appeal eventually to the House of Lords:
(i) Whatever the charterers might order,
service which fell outside the range encompassed by the owners,
of the original promise to furnish the services of the vessel,
was not one which he could be compelled to perform. The time
for measuring of the service was primarily the time when the
performance fell due.
(ii) The charterer was entitled to give
orders in advance of the time of performance, thus he was entitled
to give advance orders but the validity of those orders might
change with the passage of time.
(iii) On this case the date of the assessment
was 25th February and by that date the order originally permissible
had become illegitimate.
(iv) The submission by the owners that
the giving of an invalid order was by its nature a repudiatory
breach would be rejected. There was no commercial necessity
to hold that the issuing of an invalid order was an automatic
ground of discharge and every reason for holding that it did
not.
(v) The obligation to redeliver on time
was an ‘ innominate term’ and a short delay in redelivery
would not justify the termination of the contract. The owners’
submission that redelivery after the final date was a breach
of a condition of the contract entitling the owner to treat
himself as discharged would be rejected.
(vi) The original order had become ineffectual.
The charterers were obliged by clause 11 to replace it with
one they were entitled to give and it was clear that the charterers
had no intention of giving a valid order. The charterers’
persistence in the original order which had been rendered invalid
by the change of circumstances shows that they did not intend
to perform their obligations under the charter. They evinced
an intention to be no longer bound by the charter and this was
an anticipatory breach which entitled the owners to treat the
contract as ended – the appeal in favour of owners was
accordingly allowed.
11. The Lendoudis Evangelos 1996- Longmore
J
One time charter trip “duration
about 70/80 days without guarantee”
– the effect of the words ‘without guarantee’
– obligation of good faith in making estimate of duration
of the trip in that case the test was whether the charterers
generally believed, at the time of fixing that the trip would
last between 70 and 80 days. [In fact the voyage lasted 103
days 12 hours and 40 minutes]
Note the focus on the correct the test to be applied. The judge
was quite searching in his analysis of this. It was not, as
was suggested by the arbitrator, (purporting to follow the decision
of Mr Justice Leggatt in Benship v. Deemand Shipping –
a 1988 case only reported in the LMLN ) that the test of good
faith was whether the charterers’ original estimate was
reasonably made. That is not the test of good faith at all “If
I wrote a formula to test good faith myself, I would say that
all it requires is that the charterers’ genuinely believed
at the time of fixing that the trip would last between 70 and
80 days”.
12. Useful definitions arising from the above
(i) A legitimate last voyage –
a voyage which it is reasonably expected will be completed by
the end of the charterparty period. The owner must obey the
directions or orders if the vessel is afterwards delayed by
matters for which no party is responsible, the charterparty
continues even though it extends beyond the charterparty period
and hire is payable at the charterparty rate even though the
market has gone up or down.
(ii) An illegitimate last voyage is one
which cannot reasonably be expected to complete within the charterparty
period and the owner can refuse those orders and call for further
legitimate orders.
13. Other principles:
1. Look at the wording of the period ( remember the approach
of the arbitrator in the Sanko Honour which Hobhouse J was fairly
damning of) don’t try to cut through to get what you may
think to be a commercially sensible result
2. Does the wording provide for a fixed period (eg 6 or 12 months)
in which case some flexibility will automatically be implied-
Gray –v Christie (The Blytheville)
3. Does the wording provide for a range eg’ 4 to 6 months’
or ‘about 4 to 6 months’ ( The Democritos, the Johny
& the Gregos ) and even ‘from May 15/31, until 15/31
October’ ( as in Watson –v- Merryweather) –
remember in that case it was the addition of the handwritten
wording which the judge felt ousted the implication of a margin.
4. Does the wording exclude a margin – eg using a range
prefaced by the words ‘minimum… maximum’-
the Mareva AS 1977 Also where the words “20 days more
or less”.. (the Dione) are included – the margin
is considered to be built into the agreed period.
5. Effect of the word ‘about’ qualifying the period-
slightly confusing state of authorities – Lord Reid in
the London Explorer thought he could look at at the deleted
word to arrive at the draftsman’s intention. Another Judge,
Staughton LJ did not bother to consider the impact of the deletion
of the word ‘about’ from the printed form.
6. What margin will be implied – tends to be linked to
the original charter period The Democritos – the arbitrators
allowed a further 5 days on the original wording of ‘about
4 to 6 months’. In the Berge Tasta, Donaldson MR allowed
an overlap of 8.4 days in a case concerned with a consecutive
voyage charter for 30 months from 25 April 1969, redelivery
within 10 or 11 days of 25th October 1971 was just within a
reasonable margin. In the Dione, the arbitrators allowed 8.4
days beyond the original period of ‘6 Months 20 days’.
14. Wider Issues – the effect of
the words without guarantee – see The “Lipa”
and The “Lendoudis Evangelos”.
Both cases rely on the old authority
of Japy Freres v. Sutherland [1921] 26 Commercial Cases 227
and particularly The “Lipa” has attracted criticism.
The addition of the words “without guarantee” seems
to vitiate any meaning being given to the vessel’s details.
The arbitrators in that case, the Lipa, Timothy Rayment and
George Lugg held that rather than vitiate any meaning being
given to these details, the words should really imply a greater
tolerance than otherwise would have been there. That was held
to be incorrect by Mr Justice Smith which has caused some consternation
in the broking community. It does lend itself to what might
be called sharp practice in that having spent pages trying to
agree details of a vessel’s description all of that will
amount to nothing by the addition of the phrase at the end of
that tucked away somewhere “all details given in good
faith but without guarantee”. That case was concerned
with the description of the vessel’s speed and consumption.
The arbitrators preferred that some meaning had to be given
to the details completed in the charterparty and they considered
that the addition of the words “without guarantee”
prevented the owners from being held to an absolute warranty
but they did not rid them of all obligations from owners’
shoulders. Against that, Mr Justice Smith held that the addition
of the phrase ‘without guarantee’ meant that the
provision was not a warranty at all.
DAVID HUGHES